VolkerGround Engineering recently delivered a project at Macclesfield Wastewater Treatment Works on behalf of C2V+, a joint venture between VolkerStevin and Jacobs. The team were on site with their ABI TM13/16 SL leader rig, to complete the extraction of 266 temporary steel sheet piles.
![Piling rig on site.](/sites/vw_uk_stevin/files/styles/text_image_visual/public/2024-06/Blog%20photo%20template%20%281%29.png?itok=e-W9M9rw)
The piles had been previously installed by the VolkerGround Engineering team in March 2023, using their Volvo EC380EL excavator equipped with SG-75 vibratory Movax Hammer and Impact Hammer. Close liaison with the client ensured United Utilities employees had full access to their treatment plant, at all times on this live site.